
AWT Solids
Management Improvements
Restoring standby dewatering capacity at the Belmont Wastewater Treatment Plant by adding a 6th centrifuge, future-proofing the facility against rising solids loading.
The Challenge
The Belmont Advanced Water Treatment Plant experienced increasing solids loading that pushed its five existing centrifuges, installed in 2015 and 2016, to or near full operational capacity. With minimal redundancy built into the system, the loss of a single centrifuge represented up to a 20% reduction in total dewatering capacity, creating a significant operational risk.
The original plant design had anticipated only four centrifuges being required. As loading grew beyond projections, the fifth unit had been added, but the plant still lacked a true standby machine. Centrifuge rebuild cycles with Alfa Laval typically take 6 to 8 weeks, meaning any unplanned outage during peak loading could severely impact plant operations and compliance.
This project added a 6th centrifuge to restore a genuine standby unit and provide operational flexibility for planned maintenance rotations. The addition also future-proofed the facility by providing headroom for continued growth in solids loading beyond what the original 4-unit design envelope anticipated.
FGI Scope
- Centrifuge specifications & procurement
- Alfa Laval coordination
- Civil/structural design for new unit
- Equipment installation oversight
- Process integration & testing
- Construction documentation
- Commissioning support
Key Details
- 5 existing centrifuges (installed 2015/2016)
- Added 1 centrifuge to restore standby unit
- Manufacturer: Alfa Laval
- Exceeds original 4-unit plant design



Have a Similar Challenge?
Let's talk about how FGI can deliver on your project.



